cancel
Showing results for 
Search instead for 
Did you mean: 

WBS and funds center

Former Member
0 Kudos

Hi

Kindly explain the process flow for forming the link between WBS element and the funds center:

1. should we assign the WBS to the funds center and commit. item combination at the time of creation of PR

2. Is there single step, which assign all the WBS elements in the project, that can be assigned to the funds center and commit. item

3. Can we assign the budget to Fuds center + commit. item + WBS element combination.

regards

srikrishna

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi srikrishna,

1. To assign fund center to WBS. First you should create the fund center (FM2i). Then assign the fund center to WBS (FRC7). Assign commitment to fund center (FM9K). Then generate budget structure (FMG5).

2. There's a way to simplify the fund center assignment to WBS, it's by creating WBS Element group for all WBS in that project (CJSG). Create WBS Group before assigning fund center to WBS (FRC7), then you don't have to assign the fund center to WBS one by one, instead just assign it to the WBS Group.

While, I'm not really clear about the the 3rd question.

Hope it helps, CMIIW...I'm still learning PS also.

Cheers

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

I am clsing the thread.

Answers (0)