on 05-13-2010 12:18 PM
HI
I need a report of component costs for all networks for a project with a minor change of CN52N.
How i can link the tables from project definition to the network components and its cost and quantity.
Thanks.
Not possible with query or any other session. You will needdevelop report using table RESB(you will get network, material and qty),PRPS and PROJ( will help to get the WBS element and Project definition) in the given sequence. Also from RESB link the material to MBEW table to get its price.
Hope this can help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I agree with Mahendra Dighe, but be careful, because the user might want to get the price from last purchase using info records, from standard value or variant value of material master data.
The report should be giving the planed costs acumulated on the upper element of the project and that includes the material cost.
Read the first post of this forum, you will get PS tables.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.