Hello,
I have one problem with the programming of operations. When I create a project put the date in the past, so far good, I created the project in the past and start operations from that start date, because I have configured the program to make it forward, and I set OPU6 toward the 999 days in the past so there is no problem.
My problem is that when I move a task forward, I automatically move all programming until today and I get the following error:
"Start date is in the Past: today scheduling
Message no. C7030
Diagnosis
The start date is to determine in scheduling
In customizing, Have you defined the numbe
is Allowed to be in the Past. This number
Response System
"Today" scheduling is Carried out. "
So let me do not understand how to create the project with an earlier date and does not give me problems but as I move forward me an operation from the program all day.
I can help?
Thank you very much.