Hello,
I have a work order for which created Preq for external component with quantity 10.
Then when converting PReq into PO I have change the quantity to 5. So I have PO with quantity 5 but in the work order requirement quantity is still 10. When trying to change it on work order level I'm getting following error message: 'A purchase order already exists for purchase requisition ...'
Does anyone of you know if there is any option to synchronize quantity in work order level with PReq and PO? I know that for the sales orders there is t-code VA07 for Comparison of Orders with PReqs and POs. Do we have the same option for maintenance work orders?
Thanks in advance for any clues.
Regards,
Grzegorz