Hi...
In my business scenario, where by For one finished product, I have maintained three alternative BOMS and two Routings, so that for that material, based on the current working scenario, i have defined three production versions - alt bom 1 with routing of grp1 and other two prodn versions are for routing of grp 2 with alt bom 2 and alt bom 3 respectively.
do i have the option of selecting the particular prodn version while executing the MRP for that finished product, as when currently am executing for this, by default which i have defined in customising , alt bom 1 is chosen and pland orders are executed... but if want the second bom or third bom can i make the choice of doing that...
regards,