on 05-12-2010 4:47 AM
Hi experts!
I have 2 production order 1 and 2 for same FG.
In component of FG has component X.
Production order 1 needs 5 pcs of X. Prodcution order 2 need 5 pcs also.
And my stock is 0, 1 Fixing PR of X with 5 pcs.
The problem is when I do component ATP for production order 1. It can commit 5 pcs. But when I do component ATP for production order 2, it also commite 5 pcs. How can? Because I only have 5 pcs of X in Availble. How system can commite 2 order with 10 pcs for X?
Regards,
Tony
Dear Tony,
Not in front of system
Go to OPJJ , you can find option
Check without RLT ( Replenishment Lead time ), Mark a tick for this option
Also check the option for include all reservations for this option make it as production order released
Then create new order & check the result
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.