Former Member
May 12, 2010 at 03:47 AM

Component ATPin production order

20 Views

Hi experts!

I have 2 production order 1 and 2 for same FG.

In component of FG has component X.

Production order 1 needs 5 pcs of X. Prodcution order 2 need 5 pcs also.

And my stock is 0, 1 Fixing PR of X with 5 pcs.

The problem is when I do component ATP for production order 1. It can commit 5 pcs. But when I do component ATP for production order 2, it also commite 5 pcs. How can? Because I only have 5 pcs of X in Availble. How system can commite 2 order with 10 pcs for X?

Regards,

Tony