Hello all!
In SAP HELP for IS-U they use an example service "Dig a trench". This trench has the following characteristics:
- Length
- Depth
- Soil condition
Now I want to cost this internal service as a combination of these values, say 10 m (length) * 1 m (depth) * Hard soil = 1 EUR (Soil Condition). I want this to be from one material "dig a trench".
I know I can create a BOM or routing or individual materials for each value above and assign to the operation but then the calculation is cumbersome. There must be a standard case with classification or similar that is simple and straight forward.
PS this is one operation of a larger work represented on one service order that is sometimes billed and sometimes not.
Thanks for your input!