My company is going through SAP transition and we are not getting the information we are looking for with the support team.
Can anyone tell me if there is a way to transfer a plan (forecast) to demand management as a group (info structure/category) and by only transferring a certain date range?
Right now we are able to use MC90 and use a date range but is only for 1 material.
YPP032 does a category but no date range.
Thank you
Clayton
Hello,
In /SAPAPO/MC90 you have an option for multiple products and location selection.
Or you can use /sapapo/dmp2 to transfer data from SNP to R/3 and /SAPAPO/REL_TO_OLTP from InfoProvider to R/3
If you want to change data before transfer you can use
BAdI /SAPAPO/IF_EX_SDP_RELDATA
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.