Hi PP GURUS,
We have one scenario in which suppose We have Finished material A which is planned to deliver on 1st week of July.
Finished Material A has input component B which need to be ready 1 month before, that is in 1st week of June.
How Lead times need to be structured so that when I run MRP for FG material, Component material should have delivery date 1 month before Finish date of FG material.
Example:
FG - A MATERIAL - DELIVERY DATE - 1st WEEK OF JULY
RM - B MATERIAL - DELIVERY DATE - 1 WEEK OF JUNE
In short for production of FG material, I need to have stock of RM material 1 month before or in advance.
Regards,
Sandesh