on 05-11-2010 12:47 PM
Hi experts
We have created 2 new storage locations and moved materials into them. This has given us a problem regarding our sales orders where the item lines point to the old storage locating and not the new. Is there a smart way to change open sales orders so they point to the new location or do we only have the hard way, and do this manually for each open item line ?
Kind regaards
Jens B Olsen
SKOV A/S
Denmark
Try tcode MASS (object type: BUS2032) to update the Sloc in the sales orders.
Thanks
Swagat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thabnk you very much
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.