Hi All,
I have a basic question in Scheduling of Planned/ Process orders. I have activated capacity Planning and it is working fne. The detailed scheduling is happening for the process orders and i am able to to the dispatching in the capacity planning table in case of overload. my question is that when im running the MRP for the FG which is batch managed and with fixed lot size, suppose PIR quantity is 100 and lot size is 20 then system is doing finite scheduling for 5 planned orders of 20 each. But these orders are all getting scheduled on today. Why does the system not schedule them according to the requirements batch wise and day wise?. I need the orders to be scheduled 1 planned order per day for the next 5 days. System is doing the scheduling of all 5 orders today.
Please revert
Ariel