May 11, 2010 at 09:39 AM

[Emergency problem] MRP running----planned order and purchase order

15 Views

Hi everybody,

I met a problem when running MRP. I set a floats as 15 days, which means when I run MRP use opening period, the customer requirement within 15 days will generate PR, out of 15 days will generate Planned order.

When I run MD02, with the parameter:

Processing key: NETCH

Create purchase req.:2

Delivery schedules:3

Create MRP list:1

Planning mode:1

Then the MRP run correctly.

But when I use MD01 to run MRP through the whole plant, there is no planned order generated, all customer requirements(sales order) will generate PR no matter within or without the opening period.

I wanna know the difference between MD01 and MD02, and how to solve this tricky question.

Waiting online for help, thanks so much!!!!