Hi everybody,
I met a problem when running MRP. I set a floats as 15 days, which means when I run MRP use opening period, the customer requirement within 15 days will generate PR, out of 15 days will generate Planned order.
When I run MD02, with the parameter:
Processing key: NETCH
Create purchase req.:2
Delivery schedules:3
Create MRP list:1
Planning mode:1
Then the MRP run correctly.
But when I use MD01 to run MRP through the whole plant, there is no planned order generated, all customer requirements(sales order) will generate PR no matter within or without the opening period.
I wanna know the difference between MD01 and MD02, and how to solve this tricky question.
Waiting online for help, thanks so much!!!!