I m using program RMCP6BIN to transfer data from active version (A00) to Demand Management.

Program runs sucessfull but when i see in MD04 the PIRs (Planned Independent Requirements ) are not seen.

Spool file (log) does not show any error for these materials.

All the material master set up is ok with requirement type as 'VSF'

Version used is 4.0B.