May 10, 2010 at 01:39 PM

Result Analysis is not considering Spending on Closed Lower Level WBS

46 Views

Hi Experts,

In my company we are finding an issue related to RA on Projects.

Current when Results Analysis runs on Revenue Projects it ignores any spending on closed lower level WBS elements and makes or adjusts financial P&L postings based on what it sees.

Our Business - Accounts team wants Results Analysis should be changed to pick up spending on closed lower level WBS elements as long as the Level 1 WBS element is not closed.

Want guidance for how this can be possible through Configuration or if any OSS note for same.

or any other alternative which makes this possible.

I was thinking to add validation of not allowing lower Level WBS to close till Level-1 is closed (i.e All the WBS can be closed simultaneousl) which is ok for Business- But I want expert suggestion about whether this approach will be correct for prolem resolution.

Regards