May 10, 2010 at 10:03 AM

PO gets created with reference to WBS but having plant different from WBS

565 Views

Dear Experts,

This is in connection with PS-MM integration.

My client does not use Activity, hence all our PO's are created manually with ref. to WBS. We have multiple plants for a CoCd. As per standards each WBS is assigned to a plant and CoCd. I've realized that while creating a PO, if we use a particular WBS assigned to a plant G001 and if we use altogether different plant D001(assigned to same CoCd) in a PO, the system does not pop-up any error.

As a result of this there has been some problems for finance people. I would like to know that how can we restrict this error to happen?

I would like to know any T-code for message control in PO?

Thanks and Regards,

Manish