Hi All
I have done production order and with that status TECO and it has one component assigned to it. When i try to issue Same material to order using MIGO then it gives message "does not contain any selectable items".
Also this component is not to be backflushed.
When i confirm operation using CO11n then it allows to issue material to order.
Please explain why it is not allowed through migo.
Hi,
when u do the TECO to produciton order then it clears all the reservations so it says no selectable items are there. just enter the mvt type plant and enter then give production order it accepts the whatever material you give.
regards
ramakant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.