Hello Experts,
In my project, planning is done using activities, so ideally CN41 report displays the plan values (Proj.cost sched.000) for the network and the WBS assigned to the netwok is same.
E.g. 1000 USD planned for network = 1000 USD planned for the WBSe.
But for one of the project, I see the WBS planned value is more than that of Network though we plan only in NTW.
I can see a sales order assiged to this WBSe for which sales order billing value 1500 USD displayed in CN41 in revenue plan column.
Is there anything like sales order planning? the billing value is for revenue generation but does sales order planning also required? like to complete the sales order, how much is my plan cost? does the sales order plan cost gets updated in the WBS plan cost?
I am asking this question becasue if i look in CJ41 (Display WBS planning) I can see all the cost displayed in the column Order/network
Please clarify me on the sales order assignment.
Regards,