For a given material master we want to record different costs and lead times for cover the following:

New Part

Repair - Minor

Repair - Major

How can this be mastered in SAP. We don't want to create extended plants on the masterial master for the repair items.

I have considered split valuation, but the planned leadtime on the MRP2 tab defaults to the same value for each split valuation type.

Parts can be bought from different vendors, so I don't think a PIR is the answer.