on 05-08-2010 8:35 AM
Dear Gurus,
We have Gone -Live yesterday only, Here , The schenrio is we have 3 months plan, One month confirmed and 2 months tentative.
I have some doubts regarding MRP run and plan entery. Kindly guide me.
1. In MD61 , Should we enter plan for the month of June, July and Aug or May , june , july ?
2. If we enter plan for the month of June, July and Aug, when can we run MRP? (in the month of may or june)?
3. Should we run MRP by using MD01 with NEUPL for the first tiime , if not then ?
4.
Do i need to delete the plan for previous months , for example, if i entered plan for JUNE, JULY , AUG 2010, WHEN I run MRP in the month of say Aug, Do i need to delete the plan for June and July? Is it correct or not
Please guide.
best Regards
Dear ,
Please find the anwer your questions as below :
1. In MD61 , Should we enter plan for the month of June, July and Aug or May , june , july ?
It depends on your Repleinshment Lead time or Planned Delivery Times in Material Master for Item .Let say ,your Planned Delivery Time is 30 days and you are running MRP for the frist time and you have stock for one month replishment till you reciev the material from vendor after MRP run , then you have to run the MRP monthly basis .
2. If we enter plan for the month of June, July and Aug, when can we run MRP? (in the month of may or june)? : Running MRP is basically based on your stock situation , Safety Stock , Planned Delivery Time .If you have Plan for June , July , Aug and you want to full the demand on those month , then you need to run MRP ( Planned Delievery Time -30 /GR Processing Time 1 , Total 31 days ) backward 31 days of your planning month so that material will arraive at your stock from vendor .
3. Should we run MRP by using MD01 with NEUPL for the first tiime , if not then ? : For Frist time MRP run please folllow the below steps :
During the Go Live time MRP run : Based on WIP posting , open orders (PR,PO,SO,STPR,STO) , with Process Indicator -NEUPL,2,1,3,3,2 in MD02/MD03/MD01
But when you want run MRP normal days , with Process Indicator -NETCH
Create PR : 1 -Based on the Individual and Collective Indicator in MRP4 view (should be 2) in MM02 , PR will be generated .
Schedule Line : 1
Creatre MRP List : 3,
Planning Mode : 3
Scheduling : 2
4.Do i need to delete the plan for previous months , for example, if i entered plan for JUNE, JULY , AUG 2010, WHEN I run MRP in the month of say Aug, Do i need to delete the plan for June and July? Is it correct or not : You can delete based on your requirememnt but there are option to delete them automatically based on MRP type you are using in Material master .
Hope this will help you to figure out your issue .
Regards
JH
Edited by: Jiaul Haque on May 8, 2010 3:15 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.