sir,

In creating of planned order, I got the same date as starting date and finishing dated of the material always why ?

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

While creating the planned order system schedules the order based on the inhouse time entered in the material master MRP2 view.

For actual scheduling you need to carry out scheduling for the planned order by clicking 'Schedule planned order' icon in the planned order, in the uppaer left corner.

Before that ensure you have maintained the scheduling parameters for planned order in OPU5.

Hope this helps you.

SmanS

Former Member
0 Kudos

Dear Ashish,

are you creating plan order for FG, SFG or ROH

Check the following

In-house production time , planned delevery time , GR processing time

if possible increase the timings for Following above

then check the result

Regards

Madhu

Former Member
0 Kudos

Dear Ashish,

are you creating plan order for FG, SFG or ROH

Check the following

In-house production time , planned delevery time , GR processing time

if possible increase the timings for Following above

then check the result

Regards

Madhu

Former Member
0 Kudos

Hi,

Have you scheduled the order?? if not run the schedule order.

check the material master, you might have not maintained any inhouse production time so initially when you enter the date, based on the this it would have given you the dates. Once you schedule the order this would read your routing and give you the dates.

Regards

Mithun