on 05-07-2010 9:46 AM
Hi there;
I'm using standard evaluation "Tasks and task assignment" to have information about assignment and confirm to each resource.
But I have a problem: column "CONFIRM" only has result at task level, not for each single resource.
Is this right or you have some suggestion?
Thank you
Luciano
Edited by: Luciano Spotti on May 7, 2010 10:46 AM
Hi Luciano,
This is the correct standard behaviour, as this report shows the figures at task level.
This confirmation field is the same as the one you can find in the project, at task level on "additional data" tab.
BR
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Luciano,
Are you running task-based projects or role-based?
I'm not 100% sure, but if your project is a task-based one, all the hours reported in CATS by the resource are sent to the corresponding cProjects task withtout the resource information. Therefore, you cannot know in this evaluation report who has reported what.
Matthias