on 05-06-2010 3:30 PM
Hi, i need to control the funds at the Superior commitment item.
I have Superior commitment item 1000 and two commitment item 1001 and 1002, and i want to control at Superior commitment item 1000.
i do not know how to do it.
regards,
H
Hi,
Two different ways:
a) Create budget structure, where the budget is put on superior CI and the postings are done on other CI. Create a strategy which will define the budget address based on the attributes of the CI for posting (extract the superior CI from master data)
b) Create AVC derivation strategy for control objects which will derive the control object of superior CI based on the master data of CI for posting
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.