on 05-06-2010 2:41 PM
Hi Expers,
We want to use Factory Calender in SRM and use it in SC and PO delivery date.
We defined a new Factory Calendar and assigned the holidays we need.
1. We want to use OUR factory calendar and not the standard calendar.
Do we have to activate our factory calendar? How can we do it?
2. We want the delivery dates in SC and PO creation to be effected by the factory calendar, So the user won't be able to choose a holiday day as delivery date. Where should we define it?
Thanks & regards,
Keren
HI
It does not work as you expect since indeed we dont maintain plant data like ECC. We just pull the data from ECC and make a reference in SRM as a Business partner and enjoy the plant in SRM . do you know we even dont maintain plant price in SRM . It could be a design and architecture of issue of SRM on plant price. Still SAP research team might work on this development in coming future whatever ECC system has the same feature procurement in SRM too.
Moreover calenders are used for planiing too. check BP transaction , i have seen some where to maintain some calenders of Vendor holidays etc.
if you were refering any contract on Purchase order . it will override and delivery date picks from the contract to the Purchase order.
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Thanks for the answers.
I understood that it doesn't work as in the ECC. So we do not need to maintain plant data like ECC.
But I stil did not undestand how the system know with which calendar to work with.
The standard Factory Calendar is IL while our Factory Calendar is ZI - Where do we define that we want to use ZI calendar?
Do we define it only in the BBP_CHANGE_DEFAULT ?
I checked BP transaction but I didn't find where to maintain calender of Vendor holidays - ??
Thanks & Best regards,
Keren
Hi,
For 2, you can use one of BADI.
BBP_CHANGE_DEFAULT
BBP_DOC_CHECK_BADI
BBP_DOC_CHANGE_BADI
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Keren,
You define your calendar in SCAL. Choose Factory Calendar, click on the pencil, at the next screen click on Create, then define how you want your calendar to run, give it an ID and description, workdays, you can use the Special Rules section here as well. Once this has been all defined per your specifications you then transport it to your QAS and PRD systems and this will be the calendar that will be recognized by SAP. Hope this helps !!