Skip to Content
0
Former Member
May 06, 2010 at 01:26 PM

(ChaRM) Additional ""Action" & status required on Change Documents

311 Views

My scenario is

A Change request is approved and therefore the change document is created in "Created" status.

Currently the first action that can be undertaken is to set to "in development". Actually before this I need to be able to set the Change document to a status of "Specification" hopefully driven by an action of "Create specification" or something similar.

I have been looking at the IMG in the Define Action Profiles & Actions, however it isn't clear how I should create a new action etc.

Alternatives to setting actions are also welcome - I cannot think of another way to do this right now. Basically the specifications will not be written if the CR isn't approved but at this stage I don't have a method of holding the CR up until the specifications are done.