Former Member
May 06, 2010 at 11:28 AM

Reg: Wbs Element

37 Views

Hi,

I am using project system. while creating PO iam assigning WBS element and i created Budget for that.

My Question is

while creating PO , if PO value is 100 and tax amount is 10 how should the total value of 110 should be assigned to budget.

Regds

Sri