on 05-06-2010 11:14 AM
Hi Gurus,
we have product allocation and availability check. I want to know whether the availability check will check against the production allocation in inter company sales process.
I am having one scenario
While creating the sales order i will select the plant of another company code. So, that availability check should run against the product allocation of that respective material in that plant and confirm the dates.
So, if any one knows this process, plz guide me.
Regards,
Rajesh
Hi Rajesh,
This is not possible in R/3. This can be possible with gATP (APO).
Regards
Pankaj