Maintenance Plan: Change Yearly cycle

Former Member
0 Kudos

Hello,

We created maintenance plans for an equipment that has: Weekly, Monthly, Quarterly, and Yearly task.

THe date we initiated this maintenance plan was 6/1/2009. Is there a way to change the Yearly task date to 6/30/2010, but still keep the rest of the cycles the same dates?.

*Note we currently have a s'Schedule date of "0 days"

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If you have the exact date for a particular package in your mind, then generate a manual call in IP10 with required package.

Is there any specific reason for generating this call by system automatically?

Regards,

Vijay

Answers (2)

Answers (2)

former_member546319
Contributor
0 Kudos

Hi Jay,

I assume that you are using a Time Based Strategy Plan for this. I also assume that you have created Packages of Weekly, Monthly, Quarterly, and Yearly in the Strategy & a Suitable Task list for it.

If you have not done my assumptions, please do them first and then carryout below steps. (Aviod weekly package if you want the date exactly on 06/30/2010, if it is compulsory then you will get approximately yearly package at that time)

After you create a Strategy plan for the Equipment and save.

Set Scheduling Indicator as Time-Key Date. (Possible only with packages in multiplications of Months)

Goto IP10 and Say Start in Cycle & give the Completion date as 6/30/2009 and in the Offset select the package as Yearly.

Now all the dates will adjust based on the requirement.

Regards,

MLN Prasad

Former Member
0 Kudos

Hello,

As per you call start date the system will schedule the order on the same date you want, What exactly is your issue let me know.

If you are trying to change dates of that last yearly call then it is not possible until system reached to the immediate previous call of that.

Regards

Naveen