Hi, how to identify the pr's generated by mrp or manual? is there any difference between them to identify that this is mrp generated and or manual?
Hi,
Go to table EBAN & if field ESTKZ = B then it is MRP generated, if it is R it is manual.
Hope it clarifies.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Yadav,
one way to achieve this is
Go to MD05 & check. this report shows last planning run results ( MRP results )
Regards
Madhu