Has any one in the forum implemented or know how to achieve Automatic Scheduling of Demand (Network Order/ Network Activity ) created through PS (Project Systems) in the MRS tool. ? Using Service Orders, this is a configurable item, with a BAdI for changes if necessary. But this does not apply to Network Orders. I am considering various options, but would like to know if this could be done without modifying an SAP standard program. Options tried out include calling FM ; /MRSS/API_ASSIGNMENT_CRE, this however fails to assign the demand in the planning board, although it would assign demand in debug mode. I have equally tried Recoding and creating a BDC, but the Resource fields are not captured in the recording. Any hint would serve.