Former Member
May 03, 2010 at 08:14 PM

SRM 5.0 Service price transfered is incorrect

28 Views

Hi All,

I am having a problem when creating a PO from SRM 5.0 in R3 from a quotation.

These are the steps i am performing:

In R3

1- Create purchase requisition

2- Transfer purchase requisition to SRM with BBP_EXTREQ_TRANSFER

In SRM

3- Create a Bid invitation from the SC created in step 2

4- Create a PO from the Quotation of the Bid

In R3

PO is created with the price of the purchase requisition instead of the price of the quotation

I debugged and, from SRM the date is being filled correctly, but in function BAPI_PO_CREATE1 that is called to create the PO in R3, the service date is replaced with the data in the purchase requisition .

Do anyone know why it is modified and how can i make it take the data from the quotation??

Thanks a lot!

Nicolás.-