Hi PP Expert,

My requirement is whenever user delete / change any thing in production version in line number then system should ask change number. I checked in system thoroughly but could not get full solution. there is tab for "Assign change number" below the production version line numbers, but we can select manually , it should be automatic popup after any changing in PV. 2nd step i did to create new change number from CC01 t code but here also i am not getting PV object type that is require for assignment.

please help me on this with complete solution, all relevant answers will be appreciated.

Thanks in advance. ( its little bit urgent)

Amit Awasthi.

Accepted Solutions (0)

Answers (3)

Answers (3)

janbuchmann
Contributor
0 Kudos

Hi

Even if you were able to 'force' a new object type in, it will not yield in the desired result.

You might have to take a step back and ask the business what is behind this specific requirement. Is it for traceability purposes? Then my answer would be that the production version is nothing else than a logical parenthesis for task lists and/or BOMs. Traceability is provided on the task list and/or BOM and therefore not additionally required on the production version.

Jan

former_member600713
Discoverer
0 Kudos

Thanks Jan for your reply. I have another query , cant we create new object type for PV and assign with new change number.

Regards,

Amit.

janbuchmann
Contributor
0 Kudos

Hi

This is not possible in SAP standard. Even though object type 66 exists in check table TCC01, it is set to inactive (hard-coded) and cannot be used as an ECM object type.

Jan