Dear Experts,

Could you please explain the logic of Routing Selection in MRP

Thank you

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Nov 30, 2016 at 08:00 AM

    Hi Vivek,

    As per production version in Material Master Routing Selection involve in MRP.

    Regards,

    Chandra

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 30, 2016 at 02:15 PM

    Hi Chandra,

    Thanks for your information.

    But in Alternative Selection indicator ( MRP 4 View ) option " " , "1" based on Lot size & Alternatives.

    How Routing Selection logic works for the Option " " and "1" .

    Thank you

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 30, 2016 at 03:22 PM

    Hello

    In the SAP ERP, the routing is selected according to the selection ID, which is maintained in the customizing transaction OPU5.

    In S/4 HANA, this logic was changed and the routing is selected according to the production version only.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 13, 2016 at 09:00 PM

    Dear Almeida,

    Thanks for your valuable information and support

    Add comment
    10|10000 characters needed characters exceeded