Hello experts,

I don´t understand why some of the requirements are excluded from the MRP run. I created a PIR, and if the forecaste date is in the past the MRP excludes from the requirements creation.

If I change the requirement forecast to the future, then the MRP takes in consideration the PIR.

In Article Master data I have filled the Comsumption Mode - 4.

Where is the error?

Best regards,

Francisco

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Maybe you have defined a period of adjustment for PIRs. My answer in the following thread explains this setting in detail:

https://archive.sap.com/discussions/thread/3674867

Regards,
Caetano

Answers (1)

Answers (1)

0 Kudos

Hello Caetano,

That was it. Thanks a lot.

Best Regards,

Francisco