on 01-14-2019 10:31 PM
Hi,
We are using S&OP Heuristics to plan production. As per standard config we see the PRODUCTION (Production Receipts) based on the order finish date.
Consider a scenario we have a Production Lead Time (PLEADTIME) of 4 weeks. Demand = 500 KG, Capacity Consumption rate = 1 (1kg can be made in hr), Available capacity in week = 140 HRS.
After i run Heuristics the proposed PRODUCTION is 500 KG and the Capacity Usage (PCAPAUSAGE) = 500 HRS. So the Capacity Utilization = 499%
The production is happening over a period of 4 weeks whereas the Capacity Utilization is showing 499% in the Order Finish period. We want to model capacity in such a way that the Capacity Utilization is spread across the PLEADTIME i.e. Capacity Utilization to be 125% in each of the 4 weeks.
I understand we need to use the Capacity Consumption Policy but even while using it I was unable to model it. Currently we using the value as 0.
Any inputs will be appreciated.
Thanks,
Tejinder
Hi Tejinder,
I suggest you 2 things:
Best regards,
Matheus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tejinder
Can you use capacity consumption policy 3 to so that consumption takes place in each period?
Please check details in SAP help-
Thanks,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.