Hi Experts,

I have two requirements.

1. I want to convert the list display of the configuration result in CU50 transaction in to a ALV format. Is there any way to do the same?

2. In interface design, we have tabs for characteristic value assignment. I want to delete a particular tab since I have shifted all characteristics to the other one. System is not allowing me to do the same. Guide me how I can delete the same.

3. In MRP 3 view, we have plant specific configuration. There are 3 things to select, Variant, planning variant and configurable material. What is the purpose of these 3? What do you mean by planning variant?

Regards,

Sridharan M

Accepted Solutions (1)

Accepted Solutions (1)

Dsk
Active Contributor

1. I want to convert the list display of the configuration result in CU50 transaction in to a ALV format. Is there any way to do the same?

Answer:

1. IN cu50 it is not possible to get you any ALV format.

2. Only option is you can display as LIST

2. In interface design, we have tabs for characteristic value assignment. I want to delete a particular tab since I have shifted all characteristics to the other one. System is not allowing me to do the same. Guide me how I can delete the same.

Answer:

1. Go to Cu42

2. Here fist go to the Classassignment>valueassignment> characterstics grouping>Change/display

  • This will take you to the chars gropu over view

3.Now go to the Chargroup> it will display your group here rightside of the description in the new

pop up window you can see a deletion button , you need to dellete it here

4. once you do this the push button / tab will get deleted.

3. In MRP 3 view, we have plant specific configuration. There are 3 things to select, Variant, planning variant and configurable material. What is the purpose of these 3? What do you mean by planning variant?

Answer:

Variant : Configurable material is a MTO material in some cases a material variant will be created,

during such time we need to assighn the configurable material to the material variant

Configurable material - In case of the material varinat we need to specify that variant material is derived

from which parent configurable material

planning variant : this is used for planning

Note: Kindly avoid multiple questions in single thread.