scarp update to SL with Prd order -Confirmation

former_member182489
Active Contributor
0 Kudos

We are doing Rejection Scrap updation with 501 movt type - Plant - SL - refernce with Order (Order filed is made mandatory in display settings)

(Scrap generated unplanned while doing production process).

Now the new requirement came like , according to confirmation process - unplanned scrap will get generated and Business want to do MB!C-501 with Confirmation and not with Order.(But confirmation field is not available in option Displat screen layout )

Kindly suggect how to proceed

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Pl.make me understand as for scarp we do transfer posting (MB1B) with MVT 551 with referance to order.

Do you maen that you build up scarp stock using MB1C with Mvt 501

former_member182489
Active Contributor
0 Kudos

In Production Process - Two type sof scrap generate

1. planned - which is maintained in BOm and update with 531 mvt type

2. Unplanned - which is booked in scrap field while doing Confirmation. Suppose my Order material broke on the way/while doing maching etc . ( No where found in Inventory)

here case 2 , that scrap mat F is also sold . So an alternative method mentioned was with 501 will update scrap material and ref made as Prd Order Number(order mat Y).

It is fine , some how it meets the business req.BUt now they want with ref to confirmation But confrimation field is not avilable in Display screen for 501.

I know 501 is not for this , but for the business [purpose it was mapped like this .

551 will update o cost centre and not in INV

So kindly help me to upload the scrap with 501 with Production confirmation and not with Production Order

Edited by: manu m on Apr 27, 2010 5:52 AM

Former Member
0 Kudos

Hi,

i thnk in such cases , u need to cretae manual process order i.e which contains only scrap material and produce that scrap material .

here u just issue this scrap material to process Order and then confirmation also comes in picture which u required.

Declare the yield for the same material whcih is nothing but 101 mov.