Skip to Content

Production Order change the pick (After Completed) and how we can create a new document in EWM

Hallo,

A PICK-Warehouse Task (For a Production Order) was Confirmed even though the complete quantity was not available for an one Position. We can't change the Quantity anymore. Can anyone help me and suggest me an idea that how can we change the pick, and especially how we can create a new document?

Thank you

Add comment
10|10000 characters needed characters exceeded

  • Fur the Production order, Production Material Request (PMR) in the EWM,

    (pick) WT is confirmed even though the complete quantity was not available for one Material. Now the Problem is without changing the Quantity anymore. how can we change the pick (which is completed), and how we get the new document in EWM.


  • Get RSS Feed

2 Answers

  • Best Answer
    4 days ago

    Hello Sandrapalli,

    You can:

    1. Cancel all of warehouse task for this production order SCWM/CANCPICK

    2. Go to the outbound delivery document order and use process codes at the items level in order to adjust delivery quantity (if the godds issue was posted then you can cancel goods issue)

    3. After that you can create outbound delivery with 0 PC - then it will go qRFC message to the ERP system.

    4. After that you can close technically Production order and create a new one.

    Best regards,

    Marek

    Add comment
    10|10000 characters needed characters exceeded

  • 5 days ago

    Hello Sandrapalli,

    Maybe try the transaction SCWM/CANCPICK and then you can create ahother warehouse task for picking at the outbound delivery level.

    Best regards,

    Marek

    Add comment
    10|10000 characters needed characters exceeded

    • Hai Marek,

      Thank you. I am expecting the whole Production order newly in the EWM, like the way the production order newly replicated from the ERP System. Is there any other way to get that?

      Best regards,

      Sandrapalli