Hi Gurus,

In my inspection plan I have 2 operations, and sample drawing procedure with 2 pooled samples.

How can I adjust the plan and procedure in order to get ONLY one operation in each sample, i.e: in trx QE51N I want to see my 2 physical sample, where, in the 1st sample there is ONLY operation 0010 and in the 2nd physical sample there is ONLY operation 0020.

Regards,

MaX

Accepted Solutions (1)

Accepted Solutions (1)

former_member42743
Active Contributor
0 Kudos

removed

Former Member
0 Kudos

Fire your solution was right in the other thread, sorry I didn't understood it well.

Thanks a lot.

former_member42743
Active Contributor
0 Kudos

Not a problem. I didn't mention the sample drawing procedure as Shymal did. i assumed you had that set up already. Appears that maybe you didn't.

FF

Answers (1)

Answers (1)

Former Member
0 Kudos

Can you not you use the fixed sample primary sample with sample size =1.for each operation( or say only pooled fixed sample with sample size =1)?