on 04-24-2010 11:42 AM
Dear PP gurus
I am trying to create a production order of a material through CO01 , I am getting a error 05.05.2016 date comes after end of valid factory calendar. (Please correct
Although for all other material , no error is coming.
My factory calender is till 2015, but i am not able to understand why and how it is capturing the above date.
please help me how to correct it?
Thanks in advance
Regards
Hi,
So many suggestion you have got but I think you just check formula if any define in work center.
If it is operation time *Base qty /operation qty.
I am not sure about routing.
But in recipe we are using formula ( Qty base formula )where system takes base qty from recipe header & Operation qty takes from order qty of header.
So if we keep base qty in recipe in 1.00 QTY for that if we put operation time 16 HRs
If I create order for qty for 1000 then system calculates time 1000* 16 hrs =16000 hrs
So in your case just find any such formula is given .
Regards
SANIL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Extend the validity of the factory calender assigned to your plant in T code SCAL.
As said the date comes after the validity date of factory calender
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Aadi,
1) is it MRP created Plan order or manual created plan order
2) Check in change mode plan order for dates & change the dates in plan order itself
3) Then convert plan order to production order
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes In ca02, i double clicked on the operation, In the Extras i slected scheduling , schedule, I selected current date,
It asked for over view var, (operation segments and latest dates) , i selected first one and scheduled.
(PLease let me know if i have to select first ot second option)
Scheduled dates are 24/042010
i got a message " Scheduling data marked for material master update"
Then again i created a production order , but ufortunately same error is comin
Regards
Dear Aadi,
When your in operations screen
Extras > Scheduling > Schedule > operation overview = operation segments > Click on Gang chat icon
it should show you the days for ur base qty
then click on scheduling results then click on update material master & save
then Go to CA96
input plant
then mark a tick for ur material & click on update material master icon
then check in material master work scheduling view
Regards
Madhu
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.