Max number of activity type

Former Member
0 Kudos

Hi all,

My client has 300 employers and they manage services. Every employee has his own price and they use timesheet.

Do i have to create 300 activities to correctly track their cost? Or there is a more optimized way to do that?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

No need to maintain 300 activity.

Price is picked up with KP26 setting(combination of cost center and activity type)

Cost center and activity type is maintained in info type PA0315.

so maintain the different price with different cost center for activity type.

Thanks,

Neha Duseja