Dear ALL.

We are facing a problem for crating planned order with NETUPL processing key in MD02 , MD04,MD01

Planned orders are not getting ecreated for newly created plants when planing with NETUPL key

in existing plant it is ok .Also we have checked with different materials. Planned order are not generated for

next six month planning horizon, Planning horizon is 180 days. Only planned order are generated for APRIL.

also we have first run NEUPL for all materials , planned orders are generated for next six month . But we change requirement qty & run MRP with NETUPL , Planned orders are not getting changed.

Prashant

Accepted Solutions (0)

Answers (5)

Answers (5)

0 Kudos

We are facing a problem for crating planned order with NETUPL processing key in MD02 , MD04,MD01

These are tcodes with all it is same problem

Prashant

Former Member
0 Kudos

>

> We are facing a problem for crating planned order with NETUPL processing key in MD02 , MD04,MD01

>

> These are tcodes with all it is same problem

> Prashant

Dear Prashant,

Plz Mention clearly what is the processing key ur using

in SAP we have only NEUPL , NETPL & NETCH

But ur saying NETUPL i have never came across abt this

Can you let us know where can we find this

As mentioned by me earlier just check with planning file entries in MD21

As per ur initial ( First query ) MD02 is generating plan orders

so MD01 is lacking planning file entries, for MD02 we don't require any planning file entries

so this where your facing the problem

Hope clear to you

Regards

Madhu

0 Kudos

Dear madhu,

IT is NETPL . I am changing requirement in MD62 .

Dear JH, ABhinav,

i have checked all this still it is not working

Prashant

Former Member
0 Kudos

>

> Dear madhu,

> IT is NETPL . I am changing requirement in MD62 .

> Dear JH, ABhinav,

>

> i have checked all this still it is not working

> Prashant

Dear Prashant,

Still you have not mentioned what is the t-code ur perforimg

if it is MD01 then check for planning file entries in MD20

if not there then Create manually in MD21 or

create a variant & schedule job in OMDU

then check the result

Regards

Madhu

Anupam1143
Active Contributor
0 Kudos

HI

After Changing the PIRs then run MRP with the planning mode 3 in MD02 screen and also it is NETPL not NETUPL .

Check the planning files after changing the requirement qtys in MD20 and also check consistancies in MDRE.

Check and revert

Regards

Anupam Sharma

former_member196530
Active Contributor
0 Kudos

Dear ,

I would like to suggest you few points regarding this issue which may help you to analsyise this problem .Kindly check the following :

1.MRP Type set up (Check MRP Type -SPRO)/Planning Time Fence : Basically , MRP type also contols the creation of procurement element and change relevent to MRP based on Firming Indicator and Planning Time Fence .Please chek whether you have Firming Indicator set 0 or 1.What will happen is that if you have maintained Planning time Fence 30 days with in planning horzon 180 day , all the planned order with in PTF will not be changed based on the firming indicator set up in MRP Type.

2.Procurement Type : F/E/X and CORRECT selection of indicator in MD02/MD03/MD01 to create the Planned order (1/2)

3.Individaul and Collective Indicator : 2

4.Re-scheduling Horizon in spro-MRP-Carry on verall plant parametrs in OPJH/OPJK

5.Check Planning Entry -MDRE

Please revert and let us know .

Regards

JH

Former Member
0 Kudos

Dear Prashanth,

But we change requirement qty & run MRP with NETUPL , Planned orders are not getting changed.

Can you let us know what you have changed

it is NETPL not NETUPL

if planning horizon mainatined as 180 days then it should plan

Check for planning file entries in MD20 if your running via MD01

Regards

Madhu