Dear ALL.

We are facing a problem for crating planned order with NETUPL processing key in MD02 , MD04,MD01

Planned orders are not getting ecreated for newly created plants when planing with NETUPL key

in existing plant it is ok .Also we have checked with different materials. Planned order are not generated for

next six month planning horizon, Planning horizon is 180 days. Only planned order are generated for APRIL.

also we have first run NEUPL for all materials , planned orders are generated for next six month . But we change requirement qty & run MRP with NETUPL , Planned orders are not getting changed.