Release to SNP from DP BOM

Hello everybody,

I need a help of you.

I'm trying to do a release of a key figure in area of a DP-BOM.

I enter the transaction / SAPAPO/MC90 and release runs successfully, however, when I access the transaction / SAPAPO/RRP3 the orders are not created.

Is there any peculiarity in making a release from an area DP-BOM?

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Apr 25, 2010 at 07:46 PM

    Hi Geovana Juliani ,

    Can u check whether materials/components you have use are create in APO as location-product master data and already assigned to model 000?

    Check the date also.

    Thanks,

    Nikhil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 26, 2010 at 12:38 AM

    Hi Nikhil P, thanks for your answer.

    I checked the Key figure was being used in the release was calculated using macros. So we decided to use the transaction

    / SAPAPO/MC8E instead of / SAPAPO/MC90 that allows you to run macros before of release and so the issue is resolved.

    Thanks for your help!