Hi,

Are there any best practices for running product allocation before/after ATP ? When is allocation to be run before ATP and when should it be run after ATP ?

Thanks

GS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 23, 2010 at 10:10 PM

    Hi ,

    Availability check and Product allocation are defined in check instructions as step 1 and step 2.

    If Business needs product allocation then it can be combined with availability check as step 2.

    Most of the companies use Availability check as first step then product allocation in check instructions.

    Thanks,

    Pavan Verma