on 04-22-2010 12:45 PM
Hello all!
I have the following problem:
No simulative planned order is generated to cover the need generated by an independent requirement.
In MS04, I can see the independent requirements (VSF), but when I run MS02 for the material, nothing is generated, nor on the sub-material...
The planning scenario is using the correct planned independent requirement version.
Did I miss something?
Thanks in advance for your help.
Regards,
Rudy
Thank you for your help.
This was mainly due to a mismatch on the active version...
Regards,
Rudy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I think, Kumar, you are right.
I think it comes from the lack of definition in OPU5 (customizing).
Unfortunately, I can't test for the moment, but as soon as I can, I will post here if this was the solution...
Anyway thanks a lot for your help to both of you!
Regards,
Rudy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check you have assigned the inactive version in Planning Scenario. While updating MD61 make sure the version indicator should be inactive.
Check the Planning Scenario is released or not.
Regards
Vinoth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rudy,
1) Check in OPU5, whether you have defined Parameters for long term planning
2) Check in Work center capacity tab whether you have marked Tick for long term planning
3) you need to give in-active version for PIR's
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.