I have the following problem:
No simulative planned order is generated to cover the need generated by an independent requirement.
In MS04, I can see the independent requirements (VSF), but when I run MS02 for the material, nothing is generated, nor on the sub-material...
The planning scenario is using the correct planned independent requirement version.
Did I miss something?
Thanks in advance for your help.
Regards,
Rudy