Hi! All
1. I'm running MRP for a Material thro' MD02. with selection criteria - 3 3 1 1 2.
but my result is -
Material Plnt
PlgRunTime Read Net calc. BOM LdTmeSched Update
Material No. Plant
461 23 114 0 0 0
checked Material Master, BOM , Routing & Sale Order all the data had given correctly. But Planned Orders are not generated
can any one explain why this problem exist.
2. for some materials MRP is running but the Rescheduling dates are with past dates with Exception flag 30
can any one explain why so. .