Hi,
I have a unique factory calender to set up for a manufacturing plant. What would be the easiest way to do this ? ie set up a calender or use a calender at the work center level along with versions of available capacity ?
In case the holiday is on Friday or Monday, the arrangement is have Friday-Saturday-Sunday or Saturday-Sunday-Monday off. If the holiday is on Tuesday, they normally work on the previous Saturday, then off on Sunday-Monday-Tuesday. If the holiday is on Wednesday, it maybe combined as Monday-Tuesday-Wednesday or Wednesday-Thursday-Friday, and work on either the weekend before or after.
So you see the holidays and working days keep changing.
Thanks