01-10-2019 6:25 AM
I want to add some more value in the while calculation in the base value of Asset.
How can I do it.? I have tried to use badis but these are not getting called.
FAA_EE_CUSTOMER is not getting called.
You help is highly appreciated.
Regards,
Aneel
01-10-2019 11:01 AM
01-10-2019 12:21 PM
I have to add some value in the asset base value during calculation purpose only. Like capex value. and I am searching the calculation method where I can add more value in the base value of asset.
01-10-2019 12:22 PM
01-11-2019 2:38 PM
I have found a badi FAA_EE-CUSTOMER . I have to use set_percent_amount method for this purpose.
Anyone can have sample code for this.
?
01-11-2019 2:40 PM
Method set_percent_amount is not getting called but Set_Base_value is getitng called after assigning ZA key to Asset.
Why set_percent_amount is not being called.?