Dear Experts,
Our process is that we push a PR from ECC that creates a SC of subtype ER in SRM.
In a Z program we based on some criterion we consolidate the line items of these SCs and create BID invitation for these.
After BID invitation is created for the SCs what should be the status of these SCs in BBP_PD?
In our system it is showing
HEADER I1021 Created
HEADER I1038 Completed
HEADER I1106 Shopping Cart Ordered
HEADER I1129 Approved
0000000001 I111 Item in transfer process X
For ITEM the status is not updated to I1113 follow on documents created.
In the Z program we check if the SC Item has status I1113, if yes it means it is already processed for BID else process it for BID now. Since the SC item status is not updated properly same SCs are getting processed again .
How can we update the ITEM status for a SC of subtype ER after a BID invitation for the SC is created?
Thanks,
Anubhav
Instead of using status of the SC item as an indication, you could also use the SC item field SOURCE_REL_IND for it. If relevant Bid Invitation has been created, this field should change into one of the D, N, M or E (SRM 7 only).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.