Hi,

I have a doubt, I am implementing in a chemical industry and I have the material that is 1st getting GR from production to Tank (Insp type 04) and then at a later stage i am creating a packing order with GR of the HU (insp type 04). problem is that i have QM active for GRN from production for both points but 1 is HU managed and the other is not. System does not allow without HU tick in Inspection type setup in MM. How do i go about doing GR for both HU managed and non HU managed in the same material?

Thanks,