In MRP2 of a Material Master -Bulk material Field Activated

3209 Views

Hi

In Material Master of 421335040500 in MRP2 view procurement tab Bulk material field is activated and this material is a component included in BOM of another material 421333415050.

When i do cost estimate for the material 421333415050,I could not able to view the itemization for the given material 421335040500 and all other component from the BOM is viable in itemization.

I had checked the respective BOM,above component that has been included in the header material.

From performance assistant: F2

Dependencies

To improve system performance, you can define in the IMG for MRP that no dependent requirements are to be created for bulk material items. However, this also means that you see no information on bulk material components in the planned order or production order.

Kindly give your insight on this issue due to material marked bulk material is that a reason i could not able to view itemization in cost estimate.

Regards

Dublin